Which report goes where
Checkpoint reports go from the team manager to the project manager. Highlight reports go from the project manager to the board at a frequency the board sets. Exception reports go up when a tolerance is forecast to be exceeded. End stage and end project reports support the board's decisions at the boundaries.
Why it is like this
Each report matches a reporting line and a trigger. Routine reports are time-driven; exception reports are event-driven — which is what makes manage by exception work.
Not to be confused with
Interchangeable status updates. A highlight report is time-driven; an exception report is event-driven, and sending one does not wait for the next highlight.
In practice
An exception report proposes options; the board responds by requesting an exception plan, which replaces the plan that went out of tolerance.
Source: Managing Successful Projects with PRINCE2, 7th edition (PeopleCert, 2023) — PRINCE2 7, Appendix A — reports. Read on .
PRINCE2® is a registered trademark of PeopleCert. All rights reserved. ytyk.org is not affiliated with, endorsed by or licensed by PeopleCert. These cards are independent commentary written in our own words; no part of the PRINCE2 manual, and no PRINCE2 diagram, is reproduced here.
Say it back Check yourself
For each of checkpoint, highlight and exception: who writes it, who reads it, and what triggers it?
Answer out loud or in writing first, then open the points below.
The points a good answer makes
- Checkpoint: team manager → project manager, at the frequency set in the work package
- Highlight: project manager → project board, time-driven at the board's chosen frequency
- Exception: project manager → project board, event-driven by a forecast tolerance breach
- An exception report is followed by an exception plan if the board asks for one
Time-driven versus event-driven is the distinction that matters. An exception that waits for the next highlight report is a late exception.