How work gets sequenced, and the two kinds of value stream people conflate.
- 13 WSJF is a division, and both halves are relative Weighted Shortest Job First (WSJF) sequences work for maximum economic benefit. In SAFe it is estimated as the relative…
- 14 Cost of delay is the numerator, and it is not a price Cost of Delay (CoD) is the numerator in WSJF: the value lost by delaying or not doing a job for a period of time…
- 15 Operational and development value streams SAFe distinguishes two. An operational value stream is the sequence of activities needed to deliver a product or…
Start this pillar See the whole map
Sources: SAFe Glossary (Scaled Agile, Inc.), Scaled Agile Framework, What's new in SAFe? — the framework's own change log. Written from those texts and last checked on against reporting on them — not read line by line against the primary documents. Every card names the clause it comes from precisely so you can settle it at the source, and [email protected] is where a correction goes.
SAFe® and Scaled Agile Framework® are registered trademarks of Scaled Agile, Inc. ytyk.org is not affiliated with, endorsed by or licensed by Scaled Agile, Inc. These cards are independent commentary written in our own words; no SAFe text, graphic or Big Picture is reproduced here.