Sprint Planning has three topics, in that order
Sprint Planning addresses three topics: Why (the Sprint Goal), What (the items selected for the Sprint) and How (the plan for delivering them). It is timeboxed to a maximum of eight hours for a one-month Sprint, shorter for shorter Sprints.
Why it is like this
Starting with Why is the whole design. A team that picks items first and then writes a Sprint Goal to describe them has produced a summary of a shopping list, which cannot later be used to renegotiate scope.
Not to be confused with
A session for filling the Sprint Backlog. The Sprint Goal is created in Sprint Planning and is the Guide's first topic, not a label applied afterwards β and the Developers, not the Product Owner, select how many items to take on.
In practice
"Validate the new checkout flow end to end with real payments" is a Sprint Goal. "Finish tickets 412, 418 and 421" is the What, mislabelled.
Source: The Scrum Guide, November 2020 (Schwaber & Sutherland) β Sprint Planning. Read on .
The Scrum Guide is published by Ken Schwaber and Jeff Sutherland under CC BY-SA 4.0. These cards are independent commentary written in our own words, not a derivative of the Guide's text. ytyk.org is not affiliated with, endorsed by or licensed by Scrum.org, Scrum Alliance or the Guide's authors.
Predict Check yourself
A team fills the Sprint Backlog, then writes "deliver the selected items" as its Sprint Goal. What have they lost?
Show the answer
The ability to renegotiate scope mid-Sprint.
The Guide allows scope to be renegotiated with the Product Owner as more is learned, without affecting the Sprint Goal. A goal that just names the scope makes that impossible. The Goal no longer says anything the scope could be traded against.