Controlling a stage and managing product delivery

Controlling a stage is the project manager's day-to-day work: authorising work packages, monitoring, dealing with issues and reporting. Managing product delivery is the team manager's: accepting a work package, producing the products, and delivering them back.

Why it is like this

The split is the interface between management and delivery. It is what lets a team be internal, external or a supplier under contract without changing the method.

Not to be confused with

Two names for execution. The interface is the work package, and it is a two-way agreement — the team manager accepts it, and may negotiate it, rather than receiving it.

In practice

Checkpoint reports flow from managing product delivery into controlling a stage; highlight reports flow from controlling a stage up to the board.

Source: Managing Successful Projects with PRINCE2, 7th edition (PeopleCert, 2023) — PRINCE2 7, §17 and §18. Read on .

PRINCE2® is a registered trade mark of the PeopleCert group. ytyk.org is not affiliated with, endorsed by or licensed by PeopleCert. These cards are independent commentary written in our own words; no part of the PRINCE2 manual, and no PRINCE2 diagram, is reproduced here.

Odd one out Check yourself

Three of these happen in controlling a stage. Which one happens in managing product delivery?

  1. Authorising a work package
  2. Producing a highlight report for the board
  3. Executing a work package and producing checkpoint reports
  4. Capturing and examining issues and risks
Show the answer

Executing a work package and producing checkpoint reports

Everything the team manager does is managing product delivery; everything the project manager does within a stage is controlling a stage.