Three interests, always represented

The project board represents three interests: business (value for money — the executive), user (those who will use the outputs or be affected — the senior user), and supplier (those providing the resources and expertise — the senior supplier). All three must be represented; the executive decides.

Why it is like this

These are the three ways a project fails — unaffordable, unusable, undeliverable — and each has a different person who can see it coming.

Not to be confused with

Three people. Roles can be shared or combined, and a board can have several senior users, but the executive role is never shared: PRINCE2 requires a single point of accountability.

In practice

On a small internal project one person may hold executive and senior user. Two people jointly holding the executive role is not permitted.

Source: Managing Successful Projects with PRINCE2, 7th edition (PeopleCert, 2023) — PRINCE2 7, §7 — organizing. Read on .

PRINCE2® is a registered trademark of PeopleCert. All rights reserved. ytyk.org is not affiliated with, endorsed by or licensed by PeopleCert. These cards are independent commentary written in our own words; no part of the PRINCE2 manual, and no PRINCE2 diagram, is reproduced here.

Predict Check yourself

A board proposes two joint executives so that two departments are equally represented. What does PRINCE2 say?

  1. Not allowed: the executive is a single point of accountability.
  2. Allowed, since tailoring permits combining and splitting roles.
  3. Allowed if both report to the same programme board.
  4. Allowed only on projects above a defined size.
Show the answer

Not allowed: the executive is a single point of accountability.

Roles may be combined and shared in various ways, with the executive as the stated exception: one person, accountable. Represent a second department with senior users or senior suppliers instead.