Three interests, always represented

The project board represents three interests: business (value for money — the executive), user (those who will use the outputs or be affected — the senior user), and supplier (those providing the resources and expertise — the senior supplier). All three must be represented; the executive decides.

Why it is like this

These are the three ways a project fails — unaffordable, unusable, undeliverable — and each has a different person who can see it coming.

Not to be confused with

Three people. Roles can be shared or combined, and a board can have several senior users, but the executive role is never shared: PRINCE2 requires a single point of accountability.

In practice

On a small internal project one person may hold executive and senior user. Two people jointly holding the executive role is not permitted.

Source: Managing Successful Projects with PRINCE2, 7th edition (PeopleCert, 2023) — PRINCE2 7, §7 — organizing. Read on .

PRINCE2® is a registered trade mark of the PeopleCert group. ytyk.org is not affiliated with, endorsed by or licensed by PeopleCert. These cards are independent commentary written in our own words; no part of the PRINCE2 manual, and no PRINCE2 diagram, is reproduced here.

Predict Check yourself

A board proposes two joint executives so that two departments are equally represented. What does PRINCE2 say?

  1. Not allowed — the executive is a single point of accountability; add senior users or senior suppliers instead.
  2. Allowed, since tailoring permits combining and splitting roles.
  3. Allowed if both report to the same programme board.
  4. Allowed only on projects above a defined size.
Show the answer

Not allowed — the executive is a single point of accountability; add senior users or senior suppliers instead.

Roles may be combined and shared in various ways, with the executive as the stated exception: one person, accountable.